Solar Expansion: Fu Yu Corporation’s Path To Sustainable Power
Phase I: Commitment
. Group commits to embark on plan to utilise solar energy at its manufacturing sites
. Target to install solar panels at all suitable rooftop space in our owned factories, by 2025
. Electric Vehicle charging points to be installed.
Phase II: Singapore
. 2023: Contract signed to install Solar Panels in Singapore
. 2023: First Solar Panels Installed
. 2024: Solar Panels to be operationally ready
Phase III: New sites will progressively roll out
. 2023: Project viability assessment
. 2024: Contract to install panels to be signed
. 2024-2025: First solar panels to be installed
. 2024-2025: Solar Panels to be operationally ready.